Our Summer Gatherings Will Be Different Than Usual ☀️ | View Our Summer Calendar & Events Here >

TAGS

June 2024 – Building Update

  • Our resource consent application was lodged with council on the 16th of June, a slight delay. We pray for a smooth process as our application is considered. We continue to hope for approval in August enabling us to settle on our new home shortly thereafter.

  • We are working with Colliers to prepare for the marketing of our Gateway Properties, we anticipate that this will occur mid-July. This is a delicate balance, we obviously can’t accept any offers on our buildings without having the confidence that Council will support our move to 490 Grey Street.

  • We are scheduling a family meeting immediately following our Sunday gathering 28th of July. We hope to be able to give you a virtual walk through of the building and to speak about how you can financially support this big step in the life of our church family.